Question: What is the late start time for activity E? A. 10.7 days B. 14.8 days C. 11.8 days D. 9.1 days E. 13.3 days What

What is the late start time for activity E?
| A. | 10.7 days | |
| B. | 14.8 days | |
| C. | 11.8 days | |
| D. | 9.1 days | |
| E. | 13.3 days |
What is the slack time for activity B?
| A. | 1.6 days | |
| B. | 1.3 days | |
| C. | 1.5 days | |
| D. | 0 days | |
| E. | 2.2 days |
What is the project duration?
| A. | 18.7 days | |
| B. | 19.6 days | |
| C. | 21.8 days | |
| D. | 22.4 days | |
| E. | None of the above is correct. |
What is the maximum number of days we can delay activity D without delaying the whole project?
| A. | 0 days | |
| B. | 1 days | |
| C. | 2 days | |
| D. | 3 days | |
| E. | 4 days |
What will happen if we delay activity G by 1 day?
| A. | The entire project will not be delayed. No effect. | |
| B. | The entire project will be delayed by 0.5 day. | |
| C. | The entire project will be delayed by 1.5 days. | |
| D. | The entire project will be delayed by 0.2 days. | |
| E. | Not enough information is given to determine the effect. |