Question: What is the late start time for activity E? A. 10.7 days B. 14.8 days C. 11.8 days D. 9.1 days E. 13.3 days What

What is the late start time for activity E? A.

What is the late start time for activity E?

A.

10.7 days

B.

14.8 days

C.

11.8 days

D.

9.1 days

E.

13.3 days

What is the slack time for activity B?

A.

1.6 days

B.

1.3 days

C.

1.5 days

D.

0 days

E.

2.2 days

What is the project duration?

A.

18.7 days

B.

19.6 days

C.

21.8 days

D.

22.4 days

E.

None of the above is correct.

What is the maximum number of days we can delay activity D without delaying the whole project?

A.

0 days

B.

1 days

C.

2 days

D.

3 days

E.

4 days

What will happen if we delay activity G by 1 day?

A.

The entire project will not be delayed. No effect.

B.

The entire project will be delayed by 0.5 day.

C.

The entire project will be delayed by 1.5 days.

D.

The entire project will be delayed by 0.2 days.

E.

Not enough information is given to determine the effect.

Perform scheduling for this project. Use 1 digit after decimal point in your calculations. Activity A TG Predecessor Activity Time (days) 6.5 A 2.6 A 3.1 B 4.2 B 2.6 1.5 D, E, F 5.4 D, E, F. 6.9 G H 1.6 Immo What is the early finish time for activity E? A. 9.6 days B. 13.3 days O C. 9.1 days D. 12.4 days E. 11.7 days

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!