Question: Below is the pertinent information for a project. COST ($) ACTIVITY TIME (WEEK) NORMAL CRASH PRED. NORMAL CRASH A 6 4 $500 $700 B 8

Below is the pertinent information for a project.
Below is the pertinent information for a project. COST ($) ACTIVITY TIME (WEEK) NORMAL CRASH PRED. NORMAL CRASH A 6 4 $500 $700 B 8 5 800 950 C B 9 6 850 1,000 A, C 5 3 300 450 | |||| | [ I B 4 2 250 300 5 2 400 700 E 7 4 500 740 D 11 6 800 1,100 1 F, G, H 10 7 700 850 What is the shortest duration to complete the project? ANSWER SHOULD BE: Number only