Question: Below you can see the task information for a simple project. Per the diagram the project begins on 2 paths AB and CD. Then both

Below you can see the task information for a simple project. Per the diagram the project begins on 2 paths AB and CD. Then both paths converge on a final activity (activity F). How much time will it take to complete the project? Hint you need to draw the AON diagram using the info in the table. It should look like a house lying on its side, pointy rooftop to the right