Question: Below you will find project activities and respective time estimates: Time Estimates Activity a m b Predecessor A 1 4 7 - B 2 6

Below you will find project activities and respective time estimates:

Time Estimates
Activity a m b Predecessor
A 1 4 7 -
B 2 6 7 A
C 3 4 6 D
D 6 12 14 A
E 3 6 12 D
F 6 8 16 B,C
G 1 5 6 E,F

(a) Calculate expected time and variance for each activity

(b) Draw critical path (in your books, but do not submit here) and identify the Critical Path

(c) Calculate Early, Late, and Slack times for each activity

(d) What is the probability that the project can be completed in 34 weeks?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!