Question: beyond day 1 6 . begin { tabular } { cccccc } hline Activity & begin { tabular } { c }
beyond day
begintabularcccccc
hline Activity & begintabularc
Normal
Time days
endtabular & Normal Cost $ & begintabularc
Crash
Time days
endtabular & begintabularc
Crash Cost
mathbf$
endtabular & Immediate Predecessors
hline A & & & & &
B & & & & &
C & & & & & A B
D & & & & & B
E & & & & & C D
F & & & & & E
G & & & & & E
H & & & & & G
hline
endtabular
a What is the project's duration if only normal times are used?
The project duration is daysEnter your response as an integer.
b What is the minimumcost schedule?
With the minimumcost schedule, the project duration is square daysEnter your response as an integer.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
