Question: Bingying is working on a project that involves moving equipment and personnel to a new office. The project is being managed by the facilities department.
Bingying is working on a project that involves moving equipment and personnel to a new office. The project is being managed by the facilities department. Any coordination with other departments is occurring through normal management channels. Which project management structure is Bingying working in
Functional
Balanced matrix
Weak matrix
Strong matrix
Projectized