Question: Blooper's analysts have come up with the following revised estimates for its magnoosium mine: Variable costs, percent of revenues Working capital, percent of expected value

Blooper's analysts have come up with the following revised estimates for its magnoosium mine:
Variable costs, percent of
revenues
Working capital, percent of
expected value
Conduct a sensitivity analysis for each variable and range and compute the NPV for each. Use Spreadsheet 10.1 and accompanying
data as a starting point for the analysis.
Note: Do not round intermediate calculations. Negative amounts should be indicated by a minus sign. Enter your answer in
millions rounded to 2 decimal places.
$
(413,000,000.00
$
43,700,000.00
$
(33,200,000.00)
$
67,500,000.00
$
(5,100,000.00)
$
42,300,000.00
$
(10,200,000.00)
$
47,800,000.00
$
(36,000,000.00)
$
40,200,000.00
The column for expected is correct, the two columns labeled pessimistic and optimistic are all incorrect even if written as a decimal.
Blooper's analysts have come up with the

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Finance Questions!