Question: Blooper's analysts have come up with the following revised estimates for its magnoosium mine: Range Pessimistic Optimistic Initial investment + 25% 15% Revenues 20% +

Blooper's analysts have come up with the following revised estimates for its magnoosium mine: Range Pessimistic Optimistic Initial investment + 25% 15% Revenues 20% + 15% Variable costs + 20% 25% Fixed cost + 45% 30% Working capital + 40% 45% Conduct a sensitivity analysis for each variable and range and compute the NPV for each. Use preadsheet 10.1 and accompanying data as a starting point for the analysis. (Do not round intermediate calculations. Negative amounts should be indicated by a minus sign. Enter your answers in thousands rounded to the nearest whole dollar.) Project NPV Pessimistic Expected Optimistic Initial investment Revenues Variable costs Fixed costs Working capital
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
