Question: Both assets B and C plot on the SML. Asset B has a beta of 1.3 and an expected return of 13.1%. Asset C has
Both assets B and C plot on the SML. Asset B has a beta of 1.3 and an expected return of 13.1%. Asset C has a beta of .50 and an expected return of 7.50%. The risk-free rate is 4% and the expected return on the market portfolio is 11%. If you wish to hold a portfolio consisting of assets B and C, and have a portfolio beta equal to 1.0, what proportion of the portfolio must be in asset B?
A) 0.375
B) 0.50
C) 0.625
D) 0.75
Show work!
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts