Question: Bottom - up estimating approach begins with _ _ _ _ _ . Select answer. Question 1 4 options: Cost baseline estimates Cost budget estimates

Bottom-up estimating approach begins with _____. Select answer.
Question 14 options:
Cost baseline estimates
Cost budget estimates
Activity estimates
Work package estimates