Question: Bracket Manufacturing uses a Kanban system for a component. Daily demand is 1,300 units. Each container has a combined waiting and processing time of 0.55
Bracket Manufacturing uses a Kanban system for a component. Daily demand is 1,300 units. Each container has a combined waiting and processing time of 0.55 days. If the container size is 80 and the alpha value () is 13%, how many Kanban card sets should be authorized? Round your answer up to the whole number.
________________ Kanban card set(s)
What is the maximum authorized inventory? Use the rounded value from the previous question. Round your answer to the nearest whole number.
_______________ unit(s)