Question: Brightstar Industries You will lead a training session for new employees at Brightstar Industries. You must develop a specific schedule for the following tasks (
Brightstar Industries
You will lead a training session for new employees at Brightstar Industries. You must develop a specific schedule for the following tasks ( the estimated duration is shown in parentheses)
1. First, you need to contact the participants and explain their roles(1day). Then you must obtain approval from their department managers (3days)
2. After you obtain the approval, two tasks can begin at the same time : you can arrange the meeting room (1 day) and prepare an agenda for the initial session (8days).
3. When the agenda is ready, you can start two more concurrent tasks ; prepare the Information packets (3day ) and create visual aids (6days)
4. When the meeting room is arranged and the information packets are ready , you can send out an e-mail to participations (1day)
5. Finally , after the email is sent to participants and the visual aids are ready , you can conduct the JAD session (7days)
QUESTION:
Work Breakdown Structure (WBS table) and the corresponding Gantt Chart (diagram)
NOTE: You should develop the table and diagram and the save both as picture (for example JPEG) and then insert into your answers section. Follow the steps in this CANVAS web-page to see how to insert the picture in your discussion posting.
Step by Step Solution
There are 3 Steps involved in it