Question: Budgeted costs for Work Package Develop script - Write 1st draft $700 - Research history $1500 - Pay copy editors $250 Budgeted costs for Work
Budgeted costs for Work Package Develop script - Write 1st draft $700 - Research history $1500 - Pay copy editors $250 Budgeted costs for Work Package Prepare location - Find location $200 - Rent location $5000 - Create set $10,000 Based on the information above, assume that : 1) all activities in Work Package Prepare location are predecessors to all activities in Work Package Develop script and 2) Work Package Prepare location was completed on budget today. 42. Calculate cumulative actual costs (CAC) for the entire project at this point in time.
$ 2,450
$12,750
$15,200
$17,650