Question: Build the network and determine the critical path. Activity Predecessor Time(weeks) A - 7 B - 3 C - 1 D A,B 6 E C,B
- Build the network and determine the critical path.
| Activity | Predecessor | Time(weeks) |
| A | - | 7 |
| B | - | 3 |
| C | - | 1 |
| D | A,B | 6 |
| E | C,B | 3 |
| F | C | 4 |
| G | D,E | 3 |
| H | G | 7 |
| I | A | 5 |
| J | I,G | 2 |
| K | J | 6 |
| L | K,H,E | 3 |