Question: Build the network, define critical path and determine in which activity you have slack. Use the same project but assuming estimated times. Determine the probability

Build the network, define critical path and determine in which activity you have slack.

Build the network, define critical path and

Use the same project but assuming estimated times. Determine the probability of completing the project in 35 weeks or less.

Build the network, define critical path and

Predecessors Designation A Time (weeks) 21 5 7 B A C A D B 2 Activity Design Built Prototype Evaluate team Test Prototype Write the team report Write the report of the methods Write the final report E C, D 5 F C, D 8 G E, F. 2 Activity Designation Predecessors Optimistic | More Probable Pessimistic Expected Variance time (Pess- (op+4pro Opt/6)^2 + pes)/6 28 A 10 22 Design Built Prototype B A 4 4 10 . A 4 6 14 Evaluate team D B 1 2 3 Test Prototype E C, D 1 5 9 Write the team report F C, D 7 8 9 Write the report of the methods G E, F 2 2 2 Write the final report

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!