Question: Building an activity network using AON graph. Consider the AON graph. Activity A 1 takes 4 days; A 2 2 days; A 3 1 0
Building an activity network using AON graph.
Consider the AON graph. Activity takes days; A days; A
days; A days; A days; A days; A days; and A
days. Compute the slack time of the eight activities?
What is the critical path?
Requirement:
Graph
Building an activity network using AON graph.
Consider the AON graph. Activity A takes days; A days; A
days; A days; A days; A days; A days; and A
days. Compute the slack time of the eight activities?
What is the critical path?
Requirement:
Graph
Critical path of activities
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
