Question: Please help me solve a.Building an activity network using AON graph. b. Consider the AON graph. Activity A1 takes 4 days; A2 2 days; A3

Please help me solve
a.Building an activity network using AON graph.
b. Consider the AON graph. Activity A1 takes 4 days; A2 2 days; A3 10 days; A4 4 days; A5 2 days; A6 3 days; A7 5 days; and A8 2 days. Compute the slack time of the eight activities?
What is the critical path? c. Graph d. Table e. Critical path of activities