Question: By project day 6, activities A, B, C, and E are completed, and activities D, F, and G have begun. Compared to the projected schedule,

By project day 6, activities A, B, C, and E are completed, and activities D, F, and G have begun. Compared to the projected schedule, the project's actual schedul A. 1 day ahead of schedule B. on schedule C. 1 day behind schedule D. 2 days behind schedule