Question: By using activity compression at the lowest cost, make the best combination to shorten the project duration by 4 days. table [ [ ACTIVITY
By using activity compression at the lowest cost, make the best combination to shorten the project duration by days.
tableACTIVITYtableESTIMATEDDURATIONtabletableDURATIONWITHCOMPRESSIONtableREDUCTIONOF DAYStableCOST PERDAYtableCOST OFCOMPRESSIONK$$L$$M$$N$$$$P$$Q$$
You do not need to draw up the red diagram.
Create an Excel table where you make all the possible combinations with which the day reduction is achieved at the lowest cost.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
