Question: By using the CPM method, evaluate the critical path for a project with the following tasks. Dengan menggunakan kaedah CPM , nilaikan laluan kritikal bagi

By using the CPM method, evaluate the critical path for a project with the following tasks.
Dengan menggunakan kaedah CPM, nilaikan laluan kritikal bagi suatu dengan tugasan berikut.
Task Duration Predecessors
A 3 None
B 4 A
C 2 A
D 5 B
E 1 C
F 2 C
G 4 D, E
H 3 F, G