Question: C= 7 4 F = 1 2 5 A = 1 1 = 4 1 B = 4 6 9 K = 2 D =

 C= 7 4 F = 1 2 5 A = 1

1 = 4 1 B = 4 6 9 K = 2

C= 7 4 F = 1 2 5 A = 1 1 = 4 1 B = 4 6 9 K = 2 D = 3 G = 7 10 3 J = 9 8 E = 9 H = 3 7 Use the AOA diagram above to answer the following: The critical path is: A/ (enter the task letters exactly) The total project duration is: A/ The slack of task C is A/ Calculate Task E's ES A/ . EF A/ . LS A/ . ani LF A/