Question: (c) A small software development organization has nine developers. The development process is undefined and random, and product quality is not measured. The overall success

(c) A small software development organization has nine developers. The development process is undefined and random, and product quality is not measured. The overall success of the products depends on a few talented individuals within the organization. The organization is immature with respect to developing software. (i) What level of the Capability Maturity Model Integration (CMMI) is this organisation at now? (3 marks) (ii) What would have to change and over what period of time would the organization need to move to higher levels of the CMMI? (5 marks) (iii) Describe the policies, documentation, and staff needed to carry out the required changes