Question: C Break down the work until you can do an estimate that is accurate enough for your purposes. The WBS should conform to how you

 C Break down the work until you can do an estimate

that is accurate enough for your purposes. The WBS should conform to

C Break down the work until you can do an estimate that is accurate enough for your purposes. The WBS should conform to how you are going to schedule work. Final activities should have clearly defined start/end events. If accountability and control are important, then break the work down so that one individual is clearly responsible for the work. G All of these alternatives are correct