Question: c. Calculate the probability that the project will be completed in fewer than 30 time units Consider the network described in the table below. Activity

c. Calculate the probability that the project

c. Calculate the probability that the project will be completed in fewer than 30 time units

Consider the network described in the table below. Activity J K Immediate Predecessor(s)Pessimistic (b) Probable (m) Optimistica) 16 10 8 10 8 7 11 6 5 4 3 3 . 10 5 KM 11 4 L.N 11 8 3 J ZKF J mlin 0 P a. Draw the network diagram and fill out the chart below (by doing the forward and backward path analysis)