Question: c ) Can activity H be delayed without delaying the project completion time? If so , how many days? If $ 8 0 0 can

c) Can activity H be delayed without delaying the project completion time? If so, how many days? If $800 can be saved for each delayed day of activity F, then how much dollar can be saved keeping the project completion time unchanged?
d) Activity J needs a delayed time of one day or an extra time of one day. Is it possible by keeping the project completion time unchanged? Explain.
e) Activity A needs a delayed time of five days and activity D needs extra time of four days. Is it possible by keeping the project completion time unchanged? Explain.
f) The PM wants to shorten the duration of the activity I from 6 days to 4 days. What is the impact of this change on project completion time and critical path?
g) Activity J needs 1 day delay time and activity E needs 1-day extra time. Is it possible by keeping the project completion time unchanged? Explain.
5
Question 03:
20 marks
Activities of a project are summarized in the following table.
\table[[Activity,\table[[Immediate],[Predecessor(s)]],\table[[Duration],[(Days)]],Activity,\table[[Immediate],[Predecessor(s)]],\table[[Duration],[(Days)]]],[A,--,10,F,B,C,8],[B,-,12,G,B,C,4],[C,-,4,H,C,2],[D,A,2,1,G,H,6],[E,B,C,7,J,D,E,2]]
 c) Can activity H be delayed without delaying the project completion

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!