Question: C for 12 minutes per unit. Work stations B and C feed the parts to an assembler at workstation D, where the two parts are

 C for 12 minutes per unit. Work stations B and C

C for 12 minutes per unit. Work stations B and C feed the parts to an assembler at workstation D, where the two parts are assembled. The time at workstation D is 10 minutes. a) The bottleneck of this process is , at minutes per unit (enter your response as a whole number)