Question: ( c ) For the following task table, draw the network diagram, calculate total duration of the project, find the critical path and calculate free

(c) For the following task table, draw the network diagram, calculate total duration of the project, find the critical path and calculate free and total slack for each activity:
\table[[Task,Successor,Duration (days)],[A,L, B,3],[B,I,4],[C,-,5],[D,A, J,5],[E,J,4],[F,I,4],[G,A,3],[H,-,3],[I,C, K, H,4],[J,B, F,3],[K,-,5],[L.,I,2]]
Explain answers in details, why taking which activity at first or last and use AOA method, thanks in advance