Question: For the following task table, draw the network diagram, calculate total duration of the project, find the critical path and calculate free and total slack
For the following task table, draw the network diagram, calculate total duration of the project, find the critical path and calculate free and total slack for each activity.
Please provide the network diagram using AOA method and try to be detailed as much as possible, thanks in advance
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
