Question: For the following task table, draw the network diagram, calculate total duration of the project, find the critical path and calculate free and total slack

For the following task table, draw the network diagram, calculate total duration of the project, find the critical path and calculate free and total slack for each activity.
Please provide the network diagram using AOA method and try to be detailed as much as possible, thanks in advance
For the following task table, draw the network

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!