Question: C . Resource constrains D . Technical constrains Figure 1 . 1 : AON network for the installation of new pipes for 1 0 kilometers

C. Resource constrains
D. Technical constrains
Figure 1.1: AON network for the installation of new pipes for 10 kilometers with a period of 30 days.
16. Referring to the above Figure 1.1: Use the Laddering approach and divide each work to 4 segments (2.5 kilometers each). How many days does it take to complete the entire project?
A.10 day
2.15 days
C.20 days
D.25 Days
17. Referring to the above Figure 1.1: Use the Laddering approach and divide each work to 4 segments (2.5 kilometers each). On the 10th day, what percentage of the total work has been completed?
A.33%
B.55%
C.75%
D.85%
 C. Resource constrains D. Technical constrains Figure 1.1: AON network for

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!