Question: (c) What is the probability that that the critical path will take 18 weeks or less? (you will need to use a Z table for

(c) What is the probability that that the critical path will take 18 weeks or less? (you will need to use a Z table for this)
(d) What is the probability that that the critical path will take 26 weeks or less? (you will need to use a Z table for this)
(e) How much time must be allowed to achieve a 90% probability of timely completion? (you will need to use a Z table for this)
Preceding Activity Activity Completion Times (days) Optimistic Most Likely Pessimistic a 5 6 7 b 4 5 18 a 4 15 20 d b,c 3 4 5 a 5 16 18Step by Step Solution