Question: (c) What is the probability that that the critical path will take 18 weeks or less? (you will need to use a Z table for

(c) What is the probability that that the

(c) What is the probability that that the critical path will take 18 weeks or less? (you will need to use a Z table for this)

(d) What is the probability that that the critical path will take 26 weeks or less? (you will need to use a Z table for this)

(e) How much time must be allowed to achieve a 90% probability of timely completion? (you will need to use a Z table for this)

Preceding Activity Activity Completion Times (days) Optimistic Most Likely Pessimistic a 5 6 7 b 4 5 18 a 4 15 20 d b,c 3 4 5 a 5 16 18

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!