Question: The activities for building an prototype and related data are as follows. Activity Normal Time Crash Time Normal Cost Crash Cost Immediate Predecessor table

The activities for building an prototype and related data are as follows.
Activity Normal Time Crash Time Normal Cost Crash Cost Immediate Predecessor
\table[[Activity,\table[[Normal],[Time]],Crash Time,\table[[Normal],[Cost]],\table[[Crash],[Cost]],\table[[Immediate],[Predecessor]]],[A,3,2,1000,1500,-],[B,4,3,2000,2600,A],[C,7,3,1200,1800,A],[D,4,2,900,1200,B],[E,3,1,3500,4000,C],[F,6,4,1500,2000,DEE]]
(a) What is the project completion date?
(b) If you want to crash this project to 18 weeks, which activities need to be crashed?
(c) Use your answer to part (a) as the expected completion time of this project. Suppose the variance of the critical path is 4.
(d) What is the probability that the project will be finished in 18 weeks or less?
(e) What is the probability that the project will take longer than 20 weeks?
(f) The project manager wishes to set the due date for the completion of the project so that there is a 90% chance of finishing on schedule. What should this due date be?
 The activities for building an prototype and related data are as

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!