Question: calculate Activity Time (weeks) Immediate Predecessor(s) Activity Time (weeks) Immediate Predecessor(s) A 5 minus E 5 B B 6 minus F 6 B C 3
calculate Activity Time (weeks) Immediate Predecessor(s) Activity Time (weeks) Immediate Predecessor(s) A 5 minus E 5 B B 6 minus F 6 B C 3 A G 11 C, E D 1 A H 6 D , F Part 2 Dave's earliest start (ES) and earliest finish (EF) are: Part 3Part 4Part 5Part 6Part 7Part 8Part 9 Activity ES EF A enter your response here 5 B 0 enter your response here C enter your response here 8 D 5 enter your response here E enter your response here 11 F 6 enter your response here G enter your response here 22 H enter your response here 18