Question: A project for improving a billing process has the following precedence relationships and activity times: Activity A Activity Time (weeks) Immediate Predecessors) 7 8 D

A project for improving a billing process has the

A project for improving a billing process has the following precedence relationships and activity times: Activity A Activity Time (weeks) Immediate Predecessors) 7 8 D A 11 10 B F 5 D E F G a. Choose the correct network diagram below. WB S Enter your answer in the edit fields and then click Check Answer Activity Activity Time (weeks) 2 On critical path? Slack (weeks) A B 7 6 D 11 1 E 10 F 5 G 4 H 6 Enter your answer in the edit fields and then click Check