Question: Calculate NPV for the information given: Year 0 1 2 3 Cash flows -$1,000 $450 $460 $470 . WACC 10.00% 2.Year 0 1 2 3
Calculate NPV for the information given:
Year 0 1 2 3 Cash flows -$1,000 $450 $460 $470 . WACC 10.00%
2.Year 0 1 2 3 Cash flows -$425 $300 $325 $350 .
Calculate Projects payback ?
3. A Stock just paid a dividend of D = $1.50 . The required rate of return is r = 8.9% and the constant growth rate is g = 4.0% . What is the current stock price ?