Calculate the 'construction loan interest ' based on the property information below. Please provide Excel solution if
Fantastic news! We've Found the answer you've been seeking!
Question:
Calculate the 'construction loan interest' based on the property information below. Please provide Excel solution if possible. If not possible, please provide explanation of calculation. Thank you.
Transcribed Image Text:
SOFIA LOFTS - PROJECT INFORMATION Development Timeline Site Purchased Planning Started Construction Financing Arranged Construction Started Sales/Leasing Started Construction Completed Unit Type Studio (w/o parking) Studio Two Bedroom Three bedroom (historic house) Total Site Acquisition Cost Hard Costs Residential Units (gross) Existing House Rehab Parking Area Stairwell Soft Costs Development Cost Information Landscape/Hardscape Contractor's Fee Administrative Overhead & Expenses Contingency Subtotal - Hard Costs Architecture Landscape Architecture Structural Engineering Current Residential Information Civil Engineering Planning & Processing Consultants MEP Engineering Utility Consulting Title 24 & Survey Legal 2/1/2016 2/1/2016 9/1/2016 10/1/2016 5/1/2017 8/31/2017 Accounting, Printing & Insurance General & Administrative Property Taxes (24 months) City Fees & Permits Contingency Construction Loan Interest Subtotal - Soft Costs Total Development Cost Number of Units Square Feet 3 7 6 1 17 1,950,000 172,500 237,000 52,000 76,500 80,000 73,250 132,063 48,500 23,650 32,000 24,675 6,000 15,840 12,350 15,000 16,500 11,275 47,950 14.325 425,000 34,653 615 650 930 1,683 $ 825,000 2,773,313 727,718 $ 4,326,031 Gross Building Area (GBA) Residential Parking Total GBA Total Auto Parking Spaces Total Bike Storage Spaces Land Use Plan Buildings Landscaping/Open Space Total Vacant Units 1 1 0 0 2 Average Rents $1,425 $1,630 $2,200 $3,200 $2,114 Bldg. Area (sqft.) 13,658 Market Cap Rate Your Required ROE 3,000 16,658 Acres 0.17 0.24 0.41 16 6 Financing & Value Information Construction Loan Interest Rate Permanent Loan Interest Rate Loan to Value Amortization (years) Loan Term (years) Lender Required DCR (min.) Interest-Only Period % of Site 41% 59% 100% 3.50% 5.50% 70% 30 10 1.20 N/A 8.25% 10.0% SOFIA LOFTS - PROJECT INFORMATION Development Timeline Site Purchased Planning Started Construction Financing Arranged Construction Started Sales/Leasing Started Construction Completed Unit Type Studio (w/o parking) Studio Two Bedroom Three bedroom (historic house) Total Site Acquisition Cost Hard Costs Residential Units (gross) Existing House Rehab Parking Area Stairwell Soft Costs Development Cost Information Landscape/Hardscape Contractor's Fee Administrative Overhead & Expenses Contingency Subtotal - Hard Costs Architecture Landscape Architecture Structural Engineering Current Residential Information Civil Engineering Planning & Processing Consultants MEP Engineering Utility Consulting Title 24 & Survey Legal 2/1/2016 2/1/2016 9/1/2016 10/1/2016 5/1/2017 8/31/2017 Accounting, Printing & Insurance General & Administrative Property Taxes (24 months) City Fees & Permits Contingency Construction Loan Interest Subtotal - Soft Costs Total Development Cost Number of Units Square Feet 3 7 6 1 17 1,950,000 172,500 237,000 52,000 76,500 80,000 73,250 132,063 48,500 23,650 32,000 24,675 6,000 15,840 12,350 15,000 16,500 11,275 47,950 14.325 425,000 34,653 615 650 930 1,683 $ 825,000 2,773,313 727,718 $ 4,326,031 Gross Building Area (GBA) Residential Parking Total GBA Total Auto Parking Spaces Total Bike Storage Spaces Land Use Plan Buildings Landscaping/Open Space Total Vacant Units 1 1 0 0 2 Average Rents $1,425 $1,630 $2,200 $3,200 $2,114 Bldg. Area (sqft.) 13,658 Market Cap Rate Your Required ROE 3,000 16,658 Acres 0.17 0.24 0.41 16 6 Financing & Value Information Construction Loan Interest Rate Permanent Loan Interest Rate Loan to Value Amortization (years) Loan Term (years) Lender Required DCR (min.) Interest-Only Period % of Site 41% 59% 100% 3.50% 5.50% 70% 30 10 1.20 N/A 8.25% 10.0%
Expert Answer:
Answer rating: 100% (QA)
Calculate the total construction loan amount The construction loan amount is calculated as a percent... View the full answer
Related Book For
Business Analytics Data Analysis and Decision Making
ISBN: 978-1305947542
6th edition
Authors: S. Christian Albright, Wayne L. Winston
Posted Date:
Students also viewed these general management questions
-
X CO produces a 16 ounce can of BR at a cost of $1.80 to make and sells for $3.00. 16 ounces of BR can be further refined into 4 small tins of CP. The chrome polish sells for $5.00 per tin. Variable...
-
If the students at your school started saying thank you to friends who got flu shots, would this tend to reduce the undersupply of people who get flu shots? Why or why not?
-
Based on the excel information provided, please answer the following using excel formula's: Assume you are sitting in a board meeting discussing the firms plans for sales growth. You are telling the...
-
A company is deciding whether to produce a new gadget at a plant located in a country close to consumers at a higher labor cost and shorter lead time or to outsource it to a country with a low labor...
-
Obtain the model of the voltage vo, given the supply voltage vs, for the circuit shown in Figure. R
-
Jon bought a chargeable asset for 23,000 in May 1979. He incurred enhancement expenditure of 10,000 in June 1981 and a further 14,000 in July 1998. The asset was valued at 58,500 on 31 March 1982 and...
-
Why is the k-nearest neighbors regression called a lazy learner? a. Because k-nearest neighbors does not have embedded feature selection. b. Because the k-nearest neighbors regression requires the...
-
A little more than 10 months ago, Luke Weaver, a mortgage banker in Phoenix, bought 300 shares of stock at $40 per share. Since then, the price of the stock has risen to $75 per share. It is now near...
-
The preceding section reveals that management accounting has evolved parallel with the development of technology and business environment. It is apparent that management accounting information has...
-
Maxine, the daughter of an oil tycoon, and Fred, a young man from a working class background, were engaged to be married in Arizona. At her father's urging, Maxine hired a lawyer to draft a...
-
We represent scores of batsmen across a sequence of matches in a two level dictionary as follows: {'match1':{'player1':57, 'player2':38}, 'match2':{'player3':9, 'player1':42}, 'match3':{'player2':41,...
-
1. Draw a process flow diagram showing the major process steps, inventories, and flows.Indicate the capacity at each of the process steps. You should assume: a. 16,000 barrels per day is the average...
-
: The system of forces shown in figure is in equilibrium Calculate the unknown force 'P' and angle '0'. P 60 N 45 100 N 60 40 N 80 N
-
The following forces are acting at at a point. Find magnitude and direction of the resultant force. (i) 20 N force acting at 30 North of East. (ii) 25 N force towards North. (iii) 30 N force towards...
-
In a wheel of a bike, there are six spokes. If tensile forces in consecutive four spokes are 10N, 14N, 12N, and 5N respectively. Calculate the tensile forces in remaining two spokes. The wheel is in...
-
The Corner Convenient Store (CCS) in northern Chicago receives orders from its distributor in three days from the time an order is placed. Light Cola sells at the rate of 860 cans per day. (It can...
-
Don Griffin worked as an accountant at a local accounting firm for five years after graduating from university. Recently, he opened his own accounting practice, which he operates as a corporation....
-
Is it more appropriate to use an additive or a multiplicative model to forecast seasonal data? Summarize the difference(s) between these two types of seasonal models.
-
Suppose you are an HR (human resources) manager at a big university, and you sense that the university is becoming too top-heavy with full professors. That is, there do not seem to be as many younger...
-
Based on a given random sample, suppose you calculate a 95% confidence interval for the following difference: the mean test score for students under 25 years old minus the mean test score for...
-
A construction engineer has to inspect 5 construction sites in a 2-day inspection schedule. He may or may not be able to visit these sites in two days. He will not visit any site more than once. (a)...
-
An explosion in an LNG storage tank in the process of being repaired could have occurred as the result of static electricity, malfunctioning electrical equipment, an open flame in contact with the...
-
What conditions for the binomial distribution, if any, fail to hold in the following situations? (a) For each of a company's eight production facilities, record whether or not there was an accident...
Study smarter with the SolutionInn App