Question: Calculate the expected project completion time (in weeks) using a Gantt chart. Activity Duration Predecessors A 3 _ B 4 _ C 2 A D

Calculate the expected project completion time (in weeks) using a Gantt chart.

Activity Duration Predecessors
A 3 _
B 4 _
C 2 A
D 4 B
E 4 C
F 3 C
G 5 C , D , E
H 3 F , G