Question: Calculate the expected project completion time (in weeks) using a Gantt chart. Activity Duration Predecessors A 3 _ B 4 _ C 2 A D
Calculate the expected project completion time (in weeks) using a Gantt chart.
| Activity | Duration | Predecessors |
| A | 3 | _ |
| B | 4 | _ |
| C | 2 | A |
| D | 4 | B |
| E | 4 | C |
| F | 3 | C |
| G | 5 | C , D , E |
| H | 3 | F , G |