Question: Calculate the free float and interfering float for each of the activities shown in the activity network below in Figure 6.17. Referring to Figure 6.17
Calculate the free float and interfering float for each of the activities shown in the activity network below in Figure 6.17.

Referring to Figure 6.17 above, suppose that the duration for activity F is shortened to 8 weeks. Calculate the end date for the project. Explain your reasoning for this.
What would the end date for the project be if activity F were shortened to 7 weeks? Why?
\begin{tabular}{|c|c|c|c|c|c|c|c|c|c|c|} \hline \multirow[b]{5}{*}{ START } & 0 & 6 weeks & 6 & 6 & 3 weeks & 9 & & & & \\ \hline & \multicolumn{3}{|c|}{ A. Hardware Selection } & \multicolumn{3}{|c|}{ C. Install Hardware } & & & & \\ \hline & 2 & 2 & 8 & 8 & 2 & 11 & \multirow[b]{2}{*}{9} & \multirow[b]{2}{*}{2 weeks } & \multirow[b]{2}{*}{11} & \\ \hline & 0 & 4 weeks & 4 & 4 & 4 weeks & 8 & & & & \multirow[b]{2}{*}{ FINISH } \\ \hline & \multicolumn{3}{|c|}{ B. Software Configuration } & \multicolumn{3}{|c|}{ D. Data Migration } & \multicolumn{3}{|c|}{ H. Install and Test } & \\ \hline & 3 & 3 & 7 & 7 & 3 & 11 & 11 & 2 & 13 & \\ \hline & 0 & 10 weeks & 10 & 4 & 3 weeks & 7 & 10 & 3 weeks & 13 & \\ \hline & & Recruit Sta & & & Office Pro & dures & & User Train & & \\ \hline & 0 & 0 & 10 & 7 & 3 & 10 & 10 & 0 & 13 & \\ \hline \end{tabular}
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
