Question: Calculate the free float and interfering float for each of the activities shown in the activity network below in Figure Referring to Figure 6.17 above,

Calculate the free float and interfering float for each of the activities shown in the activity network below in Figure 


START 6 weeks 6 6 3 weeks A. Hardware Selection 2 2

Referring to Figure 6.17 above, suppose that the duration for activity F is shortened to 8 weeks. Calculate the end date for the project. Explain your reasoning for this.

What would the end date for the project be if activity F were shortened to 7 weeks? Why?
 

START 6 weeks 6 6 3 weeks A. Hardware Selection 2 2 C. Install Hardware 8 2 11 4 weeks B. Software Configuration 4 weeks D. Data Migration 2 weeks 11 H. Install and Test FINISH 3 3 7 7 3 11 11 2 13 10 weeks 10 3 weeks 7 10 3 weeks 13 F. Recruit Staff E. Draft Office Procedures G. User Training 0 10 7 3 10 10 13

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Programming Questions!