Calculate the free float and interfering float for each of the activities shown in the activity network
Fantastic news! We've Found the answer you've been seeking!
Question:
Calculate the free float and interfering float for each of the activities shown in the activity network below in Figure
Referring to Figure 6.17 above, suppose that the duration for activity F is shortened to 8 weeks. Calculate the end date for the project. Explain your reasoning for this.
What would the end date for the project be if activity F were shortened to 7 weeks? Why?