Calculate the NPV of a project that has an outlay of $300,000 and has annual net cash
Fantastic news! We've Found the answer you've been seeking!
Question:
Calculate the NPV of a project that has an outlay of $300,000 and has annual net cash flows of $80000 per year over 6 years. The project has a salvage value (disposal value) of 10% of its original value. The required rate of return for projects of similar risk is 0.11. Note that the rate of return is quoted as a decimal, e.g. 12% p.a. is written as .12 .
Related Book For
Essentials of Managerial Finance
ISBN: 978-0324422702
14th edition
Authors: Scott Besley, Eugene F. Brigham