Question: Calculate the standard deviation for the patch a-c-e-g-h. 13 Given the following table Activity Timelweeks) Immediate Predecessor A 1-2-3 A AB dummy c D F

Calculate the standard deviation for the patch

Calculate the standard deviation for the patch a-c-e-g-h.

13 Given the following table Activity Timelweeks) Immediate Predecessor A 1-2-3 A AB dummy c D F F G H END C DE F.G H 2-4-6 1-4-7 1-2-9 3-4-11 1-2-3 24. Calculate the standard deviation for the patch a-c-e-g-h. (2 Points) 1.45 1.56 1.76 1.86