Question: Given the following table: Activity Immediate Predecessor Timelweeks) A D E F 1-2-3 2-3-4 1-2-3 2-4-6 A AB dummy 1-2-9 3-4-11 1-2-3 DE 4G H

Given the following table: Activity Immediate Predecessor Timelweeks) A D E F 1-2-3 2-3-4 1-2-3 2-4-6 A AB dummy 1-2-9 3-4-11 1-2-3 DE 4G H H END (Without explanation) Calculate the expected duration for the path a-c-e-g-h Calculate the expected duration for activity C Find the z- value that the path a-c-e-g-h can be completed within 16 week Calculate the standard deviation foe the path a-c-e-g-h Find the probability that the path a-c-f-h can be completed within 16 weeks Calculate the variance for activity D
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
