Question: Calculate the three - point estimates ( weighted averages ) for the following activity durations: Optimistic ( O ) Most Likely ( ML ) Pessimistic

Calculate the three-point estimates (weighted averages) for the following activity durations:
Optimistic (O) Most Likely (ML) Pessimistic (P) Solution
Activity 15815
Activity 261521
Activity 3136
Activity 4202223
Activity 5121730
Activity 6434549
Activity 7737373
Activity 8252838