Question: Calculate the time and critical path from the data below Activity Predecessor Time (Days) A - 3 B A 14 C A 1 D C
- Calculate the time and critical path from the data below
| Activity | Predecessor | Time (Days) |
| A | - | 3 |
| B | A | 14 |
| C | A | 1 |
| D | C | 3 |
| E | C | 1 |
| F | C | 2 |
| G | D, E, F | 1 |
| H | G | 1 |
| I | H | 3 |
| J | H | 2 |
| K | I, J | 2 |
| L | K | 2 |
| M | L | 4 |
| N | L | 1 |
| O | B, M, N | 3 |