Question: Calculate the time and critical path from the data below Activity Predecessor Time (Days) A - 21 B A 14 C A 14 D B,
- Calculate the time and critical path from the data below
| Activity | Predecessor | Time (Days) |
| A | - | 21 |
| B | A | 14 |
| C | A | 14 |
| D | B, C | 3 |
| E | D | 70 |
| F | D | 70 |
| G | D | 14 |
| H | G | 1 |
| I | H | 1 |
| Activity | Predecessor | Time (Days) |
| J | D | 1 |
| K | J | 1 |
| L | D | 7 |
| M | L | 7 |
| N | D | 7 |
| O | N | 14 |
| P | O | 1 |
| Q | E, F, P | 1 |
| R | Q, I, K | 1 |
| S | M, R | 2 |