Question: Calculate the work done and the Earned Value at the end of one week in the following situation: Time estimated to complete project: 6 0

Calculate the work done and the Earned Value at the end of one week in the following situation:
Time estimated to complete project: 60
Duration of project: 2 weeks
Planned value: 30 hours per week
Actual time required over the first week: 40
Actual time required to finish the project: 45