Question: Calculate the work done and the Earned Value at the end of one week in the following situation: Time estimated to complete project: 60 Duration
Calculate the work done and the Earned Value at the end of one week in the following situation: Time estimated to complete project: 60 Duration of project: 2 weeks Planned value: 30 hours per week Actual time required over the first week: 40 Actual time required to finish the project: 45 Work done = Blank 1% Earned value = Blank 2 hours
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
