Question: Calculate the work done and the Earned Value at the end of two weeks in the following situation: Time estimated to complete project: 100 hours

Calculate the work done and the Earned Value at the end of two weeks in the following situation:

  • Time estimated to complete project: 100 hours

  • Duration of project: 4 weeks

  • Planned value: 25 hours per week

  • Actual time required over the first two weeks: 40

  • Actual time required to finish the project: 30

  • Work done = Blank 1%

  • Earned value = Blank 2 hours

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!