Question: calculate these values for the attached project, and show your work: Budgeted cost baseline (make a graph illustrating this one) Budget at completion (BAC) Planned
calculate these values for the attached project, and show your work:
- Budgeted cost baseline (make a graph illustrating this one)
- Budget at completion (BAC)
- Planned value (PV) as of May 1
- Earned value (EV) as of May 1 if the foundation work is only two-thirds complete. Everything else is on schedule.
- SV as of May 1.
- Actual cost as of May 1 is $160,000. Calculate the cost variance (CV) as of May 1.
- Schedule performance index (SPI)
- Cost performance index (CPI)
- Estimate to complete (ETC), assuming that the previous cost variances will not affect future costs
- Estimate at completion (EAC)
| Task | Date | Budgeted Amount |
| Build forms | 1-Apr | $10,000 |
| Pour foundation | 1-Apr | $50,000 |
| 1-May | $100,000 | |
| Frame walls | 1-May | $30,000 |
| 1-Jun | $30,00 | |
| Remaining Tasks | Juy 1 and beyond | $500,000 |
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock