Question: calculate these values for the attached project, and show your work: Budgeted cost baseline (make a graph illustrating this one) Budget at completion (BAC) Planned

calculate these values for the attached project, and show your work:

  1. Budgeted cost baseline (make a graph illustrating this one)
  2. Budget at completion (BAC)
  3. Planned value (PV) as of May 1
  4. Earned value (EV) as of May 1 if the foundation work is only two-thirds complete. Everything else is on schedule.
  5. SV as of May 1.
  6. Actual cost as of May 1 is $160,000. Calculate the cost variance (CV) as of May 1.
  7. Schedule performance index (SPI)
  8. Cost performance index (CPI)
  9. Estimate to complete (ETC), assuming that the previous cost variances will not affect future costs
  10. Estimate at completion (EAC)

Task Date Budgeted Amount
Build forms 1-Apr $10,000
Pour foundation 1-Apr $50,000
1-May $100,000
Frame walls 1-May $30,000
1-Jun $30,00
Remaining Tasks Juy 1 and beyond $500,000

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!