Question: 2. Earned-value analysis. A project budget calls for the following expenditures: Task Date Budgeted Amount Build forms April 1 $10,000 April 1 $50,000 Pour foundation

2. Earned-value analysis. A project budget calls for the following expenditures:

Task Date Budgeted Amount
Build forms April 1 $10,000
April 1 $50,000
Pour foundation May 1 $100,000
May 1 $30,000
Frame walls June 1 $30,000

Remaining tasks

July 1 and beyond $500,000

Define each term in your own words, calculate these values for the above project, and show your work:

  1. Budgeted cost baseline (make a graph illustrating this one)
  2. Budget at completion (BAC)
  3. Planned value (PV) as of May 1
  4. Earned value (EV) as of May 1 if the foundation work is only two-thirds Everything else is on schedule.
  5. SV as of May
  6. Actual cost as of May 1 is $160,000. Calculate the cost variance (CV) as of May
  7. Schedule performance index (SPI)
  8. Cost performance index (CPI)
  9. Estimate to complete (ETC), assuming that the previous cost variances will not affect future costs
  10. Estimate at completion (EAC)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!