Question: 2. Earned-value analysis. A project budget calls for the following expenditures: Task Date Budgeted Amount Build forms April 1 $10,000 April 1 $50,000 Pour foundation
2. Earned-value analysis. A project budget calls for the following expenditures:
| Task | Date | Budgeted Amount |
| Build forms | April 1 | $10,000 |
| April 1 | $50,000 | |
| Pour foundation | May 1 | $100,000 |
| May 1 | $30,000 | |
| Frame walls | June 1 | $30,000 |
Remaining tasks | July 1 and beyond | $500,000 |
Define each term in your own words, calculate these values for the above project, and show your work:
- Budgeted cost baseline (make a graph illustrating this one)
- Budget at completion (BAC)
- Planned value (PV) as of May 1
- Earned value (EV) as of May 1 if the foundation work is only two-thirds Everything else is on schedule.
- SV as of May
- Actual cost as of May 1 is $160,000. Calculate the cost variance (CV) as of May
- Schedule performance index (SPI)
- Cost performance index (CPI)
- Estimate to complete (ETC), assuming that the previous cost variances will not affect future costs
- Estimate at completion (EAC)