Question: CALCULATOR PRINTER VERSION BACK NEXT Exercise 23-15 x Your answer is incorrect. Try again. Urban Corporation prepared the following variance report. Fill in the missing

CALCULATOR PRINTER VERSION BACK NEXT Exercise 23-15 x Your answer is incorrect. Try again. Urban Corporation prepared the following variance report. Fill in the missing amounts or letters in the report. (Round actual and standard price answers to 2 decimal places, e.g. 2.75.) URBAN CORPORATION Variance Report-Purchasing Department For Week Ended January 9, 2017 Standard Price Price Variance Type of Materials Quantity Purchased Actual Price Explanation Rogue11 $5.15 $5.00 $4,035 Favorable Price increase Storm17 6,900 oz. $3.20 $1,380 Unfavorable Rush order Beast29 23,900 units $0.35 $478 Favorable Bought larger quantity Click if you would like to Show Work for this question: Open Show Work LINK TO TEXT Question Attempts: 1 of 5 used